Warehouse expansion: new sheet metal storage, expanded pallet storage & modern electric forklift
More capacity, more efficiency, more sustainability
In 2024, we made targeted investments in expanding our sheet metal storage and our pallet storage for spinning tools, as well as in modern, sustainable conveyor technology. The goal was to further expand our storage capacity, shorten delivery times, and make internal processes even more efficient.
New Mitsubishi electric forklift – 5.5 tons, 80V, fully electric
With the new Mitsubishi electric four-wheel forklift (5.5 t | 80V), we now work electrically and almost silently. No more hauling gas cylinders, no more reordering propellant gas – instead, low-emission, efficient work indoors and outdoors.
The benefits at a glance:
-
5.5 tons load capacity
-
80V electric drive
-
fully hydraulically adjustable forks
-
quiet operation
-
sustainable and modern conveyor technology
Expansion of our sheet metal storage – 85 cassette storage spaces
As part of the modernization, we converted our entire sheet metal storage to cassette storage plates.
This now gives us around 85 storage spaces for large-format sheets (LF). This structure ensures:
-
fast material retrieval
-
optimal overview
-
material-friendly storage
-
high availability of common sheet thicknesses
Large-format sheets (LF) always in stock
We generally keep the following materials and thicknesses permanently in stock:
Steel sheet DC01 / S355
1 mm, 1.5 mm, 2 mm, 2.5 mm, 3 mm, 4 mm, 5 mm, 6 mm, 8 mm, 10 mm, 12 mm, 15 mm, 20 mm, 25 mm
Galvanized steel sheet DX51
1 mm, 1.5 mm, 2 mm, 3 mm, 4 mm, 5 mm
Stainless steel 1.4301
1 mm, 1.5 mm, 2 mm, 2.5 mm, 3 mm, 4 mm, 5 mm, 6 mm, 8 mm, 10 mm, 12 mm, 15 mm, 20 mm, 25 mm
Stainless steel 1.4571 / 1.4404
1 mm, 1.5 mm, 2 mm, 2.5 mm, 3 mm, 4 mm, 5 mm
Aluminum AlMg3
1 mm, 1.5 mm, 2 mm, 2.5 mm, 3 mm, 4 mm, 5 mm, 6 mm, 8 mm, 10 mm, 12 mm, 15 mm, 20 mm
Sheets not in stock, special grades, custom formats, or larger quantities are of course ordered promptly and tailored to the customer.
New Euro pallet storage for spinning tools – 300 storage spaces
While we were at it, we also completely renewed our Euro pallet storage for spinning tools.
We now have around 300 storage spaces for tools available. The new storage structure ensures:
-
optimal accessibility
-
structured tool management
-
safe and space-saving storage
-
fast provisioning for production
ACQUISITION OF A COSTA MD4 1150 CVC DEBURRING MACHINE
May 2023
New deburring technology with the Costa MD4 1150 CVC
In May 2023, we expanded our machinery with a modern deburring machine: the Costa MD4 1150 CVC from manufacturer COSTA.
This investment significantly expands our manufacturing capabilities. The machine is suitable for processing steel, stainless steel, brass, and aluminum, and offers a wide range of surface finishing technologies.
These include rounding off sharp edges created during laser cutting, deburring, brushing, removing oxide layers, eliminating surface scratches, and polishing components.
With the Costa MD4 1150 CVC, we improve not only surface quality but also the reproducibility and efficiency of our products – another step toward modern, high-quality metalworking.
SECOND LASER – UFG UMFORMTECHNIK GMBH
April 2022
Second laser now in production – Mazak 6 kW Fiber
We have invested in our second laser from Mazak, a Mazak 6 kW Fiber.
We cut up to 25 mm steel and stainless steel, 20 mm aluminum, and 15 mm copper and brass.
NEW BUILDING – UFG UMFORMTECHNIK GMBH
February 2021
New press brake – Bystronic Xpert 150
We have invested in our second press brake from Bystronic, a Bystronic Xpert 150.
3,000 mm, 150 tons, 6 axes.
July 2020
Outdoor Signage – UFG-Gotha New Building
Our outdoor signage has been installed. Now we’re impossible to miss.
July 2020
OXYGEN AND NITROGEN TANKS
Both the oxygen and nitrogen tanks have been installed and connected.
July 2020
THE VIEW FROM ABOVE
View from above of our new premises.
June 2020
A LOT HAS HAPPENED INSIDE TOO.
The partition walls have been put up.
Meters of cable have been laid.
And the underfloor heating in the administrative section is also complete.
June 2020
THE PAVING WORK IN FRONT OF THE HALL IS NOW COMPLETE.
The paving work in front of the hall is now complete as well.
May & June 2020
SOLAR PANEL INSTALLATION
The company maxx solar & energie from Waltershausen started installing the solar panel system this week. (May 2020)
The solar panel installation is now complete as well. (June 2020)
May 2020
THE CLADDING PANELS ARE NOW COMPLETE
The cladding panels have been fully mounted on the base, and paving of the driveway has begun.
May 2020
DRYWALL CONSTRUCTION IN THE ADMINISTRATIVE SECTION
Drywall construction in the administrative section is in full swing!
May 2020
THE UTILITY TRENCH IS FINISHED!
The utility trench has been completed.
March 2020
INTERIOR FIT-OUT
The interior fit-out is in full swing!
The floor is now optimally prepared for further work.
The underfloor heating has already been laid, and the concrete core activation system has since been installed.
March 2020
THE FAÇADE – Part 3
The façade and roof are practically finished.
February 2020
THE FAÇADE – Part 2
The façade has been completed with sandwich panels, and the large roller door has already been installed.
February 2020
THE 4 NEW OVERHEAD CRANES
Our 4 new overhead cranes for the production area have been installed.
February 2020
Mezzanine floor as additional storage space
A mezzanine floor has been installed to provide additional storage space.
January 2020
The mezzanine floor – Part 1
Work has begun on installing the mezzanine floor.
January 2020
THE FAÇADE – Part 1
Sandwich panels are now being installed as the façade.
NEW BUILDING – UFG UMFORMTECHNIK GMBH
November 2019
Construction of the hall begins
With a slight delay, the next construction phase is now beginning – erecting the hall.
Over the coming days, the steel structure, made up of 80 tons of steel,
will be assembled step by step and welded to the foundation anchor plates.
October 2019
The Foundation
In the past few weeks, a lot has happened.
We took advantage of the beautiful summer weather to optimally prepare the ground for the start of construction on the production and administration building.
For a stable foundation, reinforcing steel cages were placed and fixed into the ground.
The anchor plates were then welded onto the cages. Finally, the ground structure was filled with concrete… and the foundation was complete.
September 2019
ALL AROUND
Every detail was considered in the construction planning. Work on the parking areas and the excavations for the flagpoles is already in full swing.
August 2019
THE LIME LAYER

For optimal stabilization, a layer of lime is milled 40 cm deep into the ground and then smoothed.
This soil-lime mixture creates a solid base for our new production hall.
August 2019
The Calm Before the Storm

Time to take a deep breath…
The ground is now ready for the next construction phase. Let’s go!
August 2019
View from Above

From a bird’s-eye view: work is progressing steadily on our new site in beautiful summer weather… and week by week, we’re getting closer to the actual start of construction.
August 2019
CREATING THE SUBGRADE

Now it’s really starting to look like a construction site…
Excavators and bulldozers are beginning to create the subgrade.
Things are moving forward!
July 2019
MOWING THE SITE

A new UFG Umformtechnik GmbH building will soon stand here. Stay tuned – we’ll keep you updated on the new building project.
May 2019
Preparations are Underway

UFG Umformtechnik GmbH’s new building project is in full swing. More information will be available here soon.
We’ll also keep you updated with photos of the ongoing construction work.